File #: 2018-0560    Version: 1
Type: Ordinance Status: Passed
File created: 11/13/2018 In control: Planning, Rural Service and Environment Committee
On agenda: Final action: 12/3/2018
Enactment date: 12/10/2018 Enactment #: 18841
Title: AN ORDINANCE certifying the existence of an emergency, requiring repair to the Stossel Bridge Right Bank Revetment, and certifying the cost incurred related to the repair work.
Sponsors: Kathy Lambert
Indexes: Bridges, Roads
Attachments: 1. Ordinance 18841.pdf, 2. 2018-0560_ATT3_Exec_Declaration_Emergency_dated June 26, 2018, 3. 2018-0560_SR_StosselBridge, 4. 2018-0560_ATT2_Transmital_Letter2018-0556
Staff: Auzins, Erin
Drafter
Clerk 11/13/2018
Title
AN ORDINANCE certifying the existence of an emergency, requiring repair to the Stossel Bridge Right Bank Revetment, and certifying the cost incurred related to the repair work.
Body
BE IT ORDAINED BY THE COUNCIL OF KING COUNTY:
SECTION 1. Findings:
A. In late March 2018, a property owner called the water and land resources division in the department of natural resources and parks to report rapidly-developing erosion damage to the Stossel Bridge Right Bank Revetment. The report from the property owner indicated a one-hundred-foot-long by eight-foot-high section of the riverward slope of the levee prism being eroded exposing gravel and sand substrate.
B. The executive determined that persons, property and commercial agricultural operations would have been threatened and damaged unless further efforts were taken to reduce the threat to life and property, including two homes, the Game Haven farm property and King County road 310th Avenue NE, which was immediately threatened and showed tension cracks indicating that the road is at imminent risk of collapse into the river.
C. The executive determined that the immediate nature required the repair work to be completed before September 30, 2018, in advance of the 2018-2019 winter flood season.
D. Based on the foregoing facts, on June 26, 2018, the executive issued an Executive Determination of Emergency in accordance with RCW 39.04.280 and K.C.C. 2.93.080, declaring that immediate steps needed to be taken to complete the repair work by September 30, 2018, and transmitted notice to the council on the same day. The executive, through the Executive Determination of Emergency, waived competitive procurement requirements in accordance with RCW 39.04.010, K.C.C. 4A.100.070 and K.C.C. chapters 2.93, 12.16 and 12.18.
E. Due to project conditions and schedules, the road services division of the King County department of transportation completed the repair work on September 28, 2018...