File #: 2003-0103    Version:
Type: Ordinance Status: Passed
File created: 3/10/2003 In control: Utilities Committee
On agenda: Final action: 4/14/2003
Enactment date: 4/28/2003 Enactment #: 14599
Title: AN ORDINANCE changing the submittal date of the wastewater CIP reallocation report to April 15 of each year; and modifying requirements for the contents of the annual wastewater CIP reallocation report and amending Ordinance 14122, Section 6, and K.C.C. 4.04.280.
Sponsors: Larry Phillips, Julia Patterson
Indexes: Budget, Wastewater
Code sections: 4.04.280 -
Attachments: 1. Ordinance 14599.pdf, 2. 2003-0103 Transmittal Letter.doc, 3. Revised Staff Report, 4. Staff Report 4-8-03
Drafter
Clerk 04/09/2003
title
AN ORDINANCE changing the submittal date of the wastewater CIP reallocation report to April 15 of each year; and modifying requirements for the contents of the annual wastewater CIP reallocation report and amending Ordinance 14122, Section 6, and K.C.C. 4.04.280.
body
BE IT ORDAINED BY THE COUNCIL OF KING COUNTY:
SECTION 1. Ordinance 14122, Section 6, and K.C.C. 4.04.280 are each hereby amended to read as follows:
Wastewater capital improvement budgeting.
A. This section establishes procedures required for flexible response budgeting provisions applicable to the wastewater CIP beginning in 2002. Except as specifically provided in this section, budgeting for the wastewater CIP shall be in accordance with other applicable county law.
B. To allow reprogramming flexibility needed to respond in a timely manner to events beyond the control of the wastewater treatment division that result in temporary postponement or acceleration of wastewater CIP projects allocated in the current budget year, and not withstanding any other provision of county law, current-year budget authorization for the wastewater CIP shall be appropriated at the total CIP fund level rather than CIP project level. Wastewater CIP project budget allocation substitutions may take place during the budget year among the projects specifically adopted in the current six-year wastewater CIP together with carryover projects from previously adopted plans in accordance with the procedures in this section without the need for the enactment of amendatory appropriations ordinances; provided, however, that allocation substitutions for wastewater asset management projects may be done only between projects within wastewater asset management project categories, and not between projects in different wastewater asset management project categories.
C.1. Implementation of the wastewater CIP shall be in accordance with the project funding priorities and project fundin...

Click here for full text