File #: 2023-0216    Version: 1
Type: Ordinance Status: Passed
File created: 7/18/2023 In control: Local Services and Land Use Committee
On agenda: Final action: 9/5/2023
Enactment date: 9/13/2023 Enactment #: 19662
Title: AN ORDINANCE approving the Sammamish Plateau Water and Sewer District Wastewater Comprehensive Plan Update and General Sewer Plan dated February 2023.
Sponsors: Rod Dembowski
Indexes: Sammamish, City of, Water and Sewer Districts
Attachments: 1. Ordinance 19662, 2. Ordinance 19662 Attachment A, 3. 2023-0216 transmittal letter, 4. 2023-0216 Fiscal Note, 5. 2023-0216 Sammamish Plateau Water & Sewer District Wastewater Comprehensive Plan Update and General Sewer Plan (February 2023), 6. 2023-0216 Legislative Review Form, 7. 2023-0216_SR_SammamishPlateauSewer
Staff: Micklow, Andy

Drafter

Clerk 06/14/2023

title

AN ORDINANCE approving the Sammamish Plateau Water and Sewer District Wastewater Comprehensive Plan Update and General Sewer Plan dated February 2023.

body

STATEMENT OF FACTS:

1.  King County has adopted K.C.C. chapter 13.24, which requires approval of comprehensive plans for water and sewer utilities that provide service in unincorporated King County as a prerequisite for operating in unincorporated King County, receiving approval for annexation proposals, being granted right of way franchises, and being given approval for right of way construction permits.  K.C.C. chapter 13.24 prescribes the requirements for approval of such plans, including consistency with state and local planning requirements.

2.  The Sammamish Plateau's last sewer plan was approved in 2015.  King County regulations require wastewater system plans to be updated every six years.

3.  The Sammamish Plateau Water and Sewer District's wastewater system has a service area within King County and has adopted a wastewater comprehensive plan update ("the plan").

4.  King County has adopted a Comprehensive Plan that includes policies F-101 through F-264, the applicable portions of which address wastewater policies for facilities and services; these wastewater policies call for consistency with other adopted plans, pursuit of reclaimed water, water conservation and protection of water resources.

5.  K.C.C. chapter 13.24 requires the utilities technical review committee to review and make a recommendation to the King County executive and council on the plan, the requirements under K.C.C. chapter 13.24 and consistency with the King County Comprehensive Plan.  The utilities technical review committee has reviewed the planning data and system operations and has found:

  a.  The plan considers population and employment forecasts developed by the Puget Sound Regional Council;

  b.  The system's service area is in unincorporated King County;

  c.  The capital facility plan is adequate to meet anticipated facility and service needs;

  d.  The plan is consistent with applicable Washington state water quality laws; and

  e.  The plan is consistent with other pertinent county adopted plans and policies.

6.  Washington state Department of Ecology approved the plan on April 27, 2023.

7.  Under the State Environmental Policy Act the system completed an environmental check list and the district issued a Determination of Nonsignificance for the plan approval on September 21, 2022.  There were no appeals.

8.  The system's operations and facilities meet multiple existing statutory, administrative, and planning standards.  As the system's operations, facilities, and planning meet the requirements of the King County Code and are consistent with the King County Comprehensive Plan, the utilities technical review committee has recommended approval of the plan.

                     BE IT ORDAINED BY THE COUNCIL OF KING COUNTY:

                     SECTION 1.  The Sammamish Plateau Water and Sewer District Wastewater

Comprehensive Plan Update and General Sewer Plan dated February 2023, Attachment A to this ordinance, is hereby approved as a comprehensive wastewater plan.